Sunday, 12 July 2015

DB awards €312 million Rastatt tunnel construction project


DB awards €312 million Rastatt tunnel construction project

German Rail (DB) has awarded a €312m contract award to a joint venture of Ed Züblin and Hochtief to build the 4270m Rastatt tunnel as part of the project to enhance the Karlsruhe – Basle corridor for 250km/h operation.

The twin-bore tunnel will be linked every 500m by transverse tunnels. The construction work is considered technically challenging because of the geological and hydrological conditions and the shallow depth to a maximum of 20m. According to DB by using special materials and measures such as temporary embankments, soil stabilization or soil freezing, the most critical sections are definitely manageable.Read complete story at http://www.tendersontime.com/blog-detail/db-awards-euro312-million-rastatt-tunnel-construction-project-258.php